For the 3,000 passengers sweltering in the tunnel at Oxford Circus on Monday, it was just another rush-hour delay on the Victoria line. For the future of the Tube, it was more frustrating.
The broken-down train was one of the 10 spanking new, fully automatic, £10 million machines central to the Victoria line's £900 million upgrade.
Already they have been tested on the line for a year. Still they suffer computer software problems. And this is just the leading edge of the dramatic upgrades planned for almost the whole network.
New kit always causes problems: trains introduced on the Northern line in 1996 broke down for years, justifying the “misery line” nickname. The Victoria line upgrades are on schedule and on budget. But today Tube users are facing the reality of state-of-the art trains and signalling systems being tested live on the world's oldest underground railway system.
Combined with the threat of savage Government cuts, such challenges suggest we may have much longer to wait for the new Tube we were promised in 2003, when the first of the Public Private Partnership (PPP) deals for the network was signed and control of London Underground passed to the Mayor.
That we need a new Tube is beyond doubt. Never mind the delays and crumbling stations suffered by passengers: go behind the scenes and it's clear that this is a network in desperate need of investment.
At the Earl's Court control room on the District line, most of the technology is stuck in 1961, when it was built. “I first came here in 1977,” jokes Howard Collins, LU's chief operating officer, “and you still can't stick anything into the wall because of the asbestos.”
I'm down in the interlocking machine room, the guts of the District line's signaling system — effectively the brain of the line. The technology is mechanical levers powered by air pressure, directed by hole-punch reels driven by Hewlett Packard HP1000s, a 1960s computer system discontinued a decade ago. It looks like the traffic-control computer sabotaged in The Italian Job (1969) — only scruffier and with household fans rigged up to keep the heat down.
Transport Commissioner Peter Hendy is more pithy: “The signaling is all clapped out.”
This is the heart of the problem, and it's a big job — roughly like rewiring your whole house, only without stopping anything running. On Monday the Metropolitan line will get the first of the “sub-surface” lines' 191 new trains, complete with air conditioning. But as Collins admits: “It's like taking the poshest car imaginable and then driving it down a farm track.” Without new signalling and track, the new trains will make little difference to journey times.
The PPP, a mind-bendingly complex 30-year deal contracting out maintenance and upgrading, was supposed to fix all this. The plan was to increase the Tube's capacity to serve a bigger, more prosperous London, as well as making the Tube more pleasant to use. Instead of about 24 trains an hour at peak times, there would be nearer 36.
You could be forgiven if you hadn't noticed — despite nearly £12 billion being spent since 2003. Many of the improvements have been peripheral — new track on outlying sections, spruced-up stations — or else add-ons such as the Oyster system.
The major work fell rapidly behind and costs ballooned. The two consortia of engineering contractors involved, Tube Lines and Metronet, argued bitterly with Transport for London.
Metronet collapsed in May 2007 under a mountain of debt and uncontrolled costs. It had been responsible for the Victoria, Bakerloo, Waterloo and City and Central and “sub-surface” lines (the earliest, shallow Underground lines — Circle, District, Hammersmith and City, Metropolitan and East London). In May 2008, it was transferred to TfL.
Then last year the other contractor, Tube Lines, responsible for the Jubilee, Northern and Piccadilly lines, started to wobble, after admitting that the Jubilee line upgrade was far behind schedule.
A major stand-off developed with TfL over the costs of the next stage of the work, starting next year — although the PPP's arbiter conceded that the cost was £400 million more than TfL claimed. Faced with collapse, Tube Lines was bought out for £310 million by TfL last month.
Imperial College's Professor Stephen Glaister, a former board member of TfL and a director of Tube Lines, blames Gordon Brown, who forced the PPP model on Mayor Ken Livingstone. “Brown thought PPP was a cost-reducing way of getting the work done,” recalls Glaister. “That simply was not realistic.”
A TfL report last week warned of serious new delays to both the Jubilee and Northern lines (see box). One Jubilee line driver told me: “There's a general lack of confidence among drivers. When we test it at weekends, we'll have a good afternoon when it runs fine and then the system falls over and we have hours of delays.”
The Mayor has promised that line closures on the Jubilee and Northern lines will be kept to a minimum — but that will prolong the job.
Meanwhile, there are serious doubts whether the lines that were always further along in the schedule — such as the Piccadilly and Bakerloo — will ever now get their upgrade.
Then there's the money. It was already questionable whether TfL could afford the job.
Glaister warns: “There is a big black hole and TfL are either going to have to find the money elsewhere or slow down the whole programme.”
And there is the prospect of the Department for Transport passing on cuts of up to 40 per cent.
There is also competition for funds from separate Crossrail projects. The LSE's Tony Travers is pessimistic: “The Treasury just don't trust London Underground any more.”
Hendy concedes that “in extremis” a 40 per cent cut in funding would mean not being able to upgrade signalling on the sub-surface lines. He warns: “The risk then is that the system falls over more and more.” Glaister adds: “I'm really concerned that the Northern line is going to become dreadfully unreliable.”
Business leaders are clear, though: without a revamped Tube, London will start to grind to a halt. Passenger numbers have risen steadily since the mid-1980s: there are now 3.5 million journeys each weekday and sometimes more than four million. London's projected future growth will push it past breaking point.
Peter Hendy is defiant: “The Mayor will go down fighting for this.”
Prepare for a battle royal between Boris Johnson and the Chancellor over the future of the rails beneath our feet.
Victoria Line
Still scheduled for completion in spring 2012. A new signalling system is ready to go live, while most of the work on renewing track and ventilation systems is complete. The main hold-up now is the wait for the rest of the 47 new trains, arriving at a rate of about one a fortnight from engineers Bombardier.
Jubilee Line
Originally contracted to Tube Lines, the main part of the upgrade to the Jubilee line is to its signalling system, designed by French electronics group Thales. Originally scheduled for completion in December 2009, it fell badly behind: Tube Lines underestimated the difficulty of developing the system software. Extra weekend closures — 146 to date, which have led to all sorts of problems for the O2 arena at Greenwich, for example — have still not anywhere near ironed out the bugs in the system. A recent TfL report says that it is unlikely to be complete before February 2011.
Circle, District, Hammersmith and City and Metropolitan Lines
These sub-surface lines are the focus for the next major tranche of investment, £4.5 billion over seven years. From next week, new trains will start to run here, starting with the Metropolitan line. By 2015 all these lines will have the new trains (cost: £1.5 billion) although some platforms will need lengthening to accommodate them. Work on new signalling will begin next year. Expected completion of the whole upgrade: 2017.
Northern Line
New signalling for the Northern line was originally contracted to Tube Lines and scheduled for completion by December 2011. By this month, work was supposed to be 72 per cent complete — in fact, only 10-12 per cent has been done. A report for TfL this month by contractors Serco notes that “slippage experienced to date suggests that if this programme were to proceed then it is likely that the upgrade would not be complete until late 2013” and that “even this estimate may be optimistic”.
Piccadilly Line
New trains and signalling were originally scheduled for completion by 2014. Future now very uncertain: TfL are cagey about the timetable and even 2017 is now seen as optimistic by insiders. By then its existing trains will be 40 years old.
Bakerloo Line
The last line to be upgraded: new trains and signalling originally scheduled for 2020. When it gets done is now anyone's guess.
Reader views (14)
Behzad – Tube Lines was responsible for the Jubilee Line until May this year, a private consortium created by Amey PLC and Bechtel. Rather than being forced to sort it out Boris paid them £310m to walk away from the mess they’d made so the likelihood of anyone ever getting being held to account is no-existent.
- ASLEF shrugged, E London, UK, 03/08/2010 16:54
Report abuse
That complete idiot, Broonie, we had as our last chancellor then PM was responsible for the absurd PPP financing structure that is largely responsible for today's mess. So now here we are with a crumbling tube infrastructure and he gets to go and preach to the (non listening world) at our expense about Africa. Somebody please throttle him !!!
- Kevin Bollox, London, 31/07/2010 09:27
Report abuse
When are we going to see someone held to account for the monumental cock-up that is the Jubilee line upgrade? Never mind the enormous cost, what about the incredible inconvenience suffered by passengers living on the line? 146 weekends! And on a line for which a good chunk was only built ten years ago. What other city on earth puts up with that kind of nonsense?
- behzad, London, 31/07/2010 01:12
Report abuse
Mike – 11.4m spent on the Borismaster wouldn’t fix much on the Tube, think bigger friend.
Therealvicz – at the moment we are one of the most expensive mass transit system in any major city, the reason other cities subsidise is that they recognise that to keep a city working you need cheap public transport. Raise the prices too much and we start to lose passengers, the City becomes unworkable, the country loses the huge revenues London generates. Even the Tories have consigned that sort of Thatcherite monetarist dogma to the dustbin!
- ASLEF shrugged, Leyton, UK, 30/07/2010 20:20
Report abuse
How mind-numbingly incompetent do you have to be to lose money running the tube? You could triple fairs and still not have enough capacity to satisfy demand. It should not be run as a charity or state subsidised nonsense, it should be run as a proper business with realistic fairs and therefore provide the sort of return on investment that got it built in the first place.
- therealvicz, Notlondon uk, 30/07/2010 16:35
Report abuse
I blame Boris - he's squandered millions on pointless 'semi-routmasters' that cost a fortune and carry less passengers, when he could have used the money for the tube.
- Mike, London, 30/07/2010 16:12
Report abuse
Before I was a Train Op I was a Stations H&S Rep and got to see the inside of plenty of SERs so I do know what state some of these places are in but when did we ever have the investment to make these replacements? PPP was meant to deal with this, up till then central government, who were responsible for the Tube until it was handed over to the Mayor, had dodged the issue. With the current squeeze on funding it is probably going to take a massive failure for the current administration to face up to the problems, until that happens we are going to have to struggle on.
How exactly would you change over from DC to AC? You’d have shut down whole lines one while the power supply was converted unless there is some way trains could run on both but even then you’d have to withdraw stock for adaption. When exactly would we shut down the Central Line for months, or the Piccadilly, or any line? As for mounting the traction rail on the side of the tunnel the vast majority of the Tube is above ground, the Central Line is “open section” west of White City and east of Leyton. Pneumatic tyres would hopefully be puncture free but if you imagine that 150-ton of train is ever going to be anything like silent you are grossly deluded.
Tommo, and anyone else, these might all be good ideas in theory but please, please, please do put some thought into how this would all be achieved within practical and economical constraints.
- ASLEF shrugged, Leyton, UK, 30/07/2010 11:32
Report abuse
The best solution would be to scrap Crossrail and spend the money on the tube. If we don't do this we risk ever more disrupted tube journeys.
- Richard, Hoxton, 29/07/2010 22:10
Report abuse
You know it's a problem when someone's made a facebook group...
- Jim, London, 29/07/2010 21:38
Report abuse
ASLEF Shrugged
With respect, I am saying that these changes could have been accomplished already with the amount of money spent propping the signalling and power generating/distribution infrastructure up. The repairs are only ever temporary measures which last until the next failure. As a driver you probably have never seen the control mechanisms in some of LUL's trackside equipment rooms. To do so would give you a better understanding that drastic action has to be faced sooner rather than latter - or one day totally loose the system for days on an end.
- Tommo, Brighton, England, 29/07/2010 21:15
Report abuse
Tommo you are living in dreamland, the sort of investment required to make all these changes would be immense and is simply not available. As for George, the only thing failry simple is comments like yours, you obviously have no idea of what goes into running the Tube.
My respect to the author of this piece, a thoroughly well thought out and researched article, something sadly we have not come to expect from the Standard when the Tube is discussed. I will keep my eye out for Andrew Neather articles in future.
Easy to blame Gordon Brown but the private companies that made up Tubelines and Metronet didn’t stop to point out that the expectations being placed upon them were unrealistic, they and the City just sat back and sucked up public money until it was taken away from them. And the Standard did little in way of objection while the much derided RMT were going on strike to voice their opposition to the proposals, not that it had any effect but at least they tried in their own inadequate fashion.
I’m am ASLEF driver on the Central Line, I’ve not been on strike for the whole seven years I’ve been doing the job but it is clear that the current administration is more concerned with saving money than keeping the system that delivers the wealth of London running. The City without the Tube will not stand but dogmatic monetarist principles neglect the simple truth that without us London ceases to function. Not everything can be explained by the balance sheet.
Bravo.
- ASLEF shrugged, Leyton, UK, 29/07/2010 19:36
Report abuse
New rolling-stock and revamped signalling doesn't make the underground a modern or reliable system. Behind all these peripheral changes is an infrastructure so unbelievably antiquated that it should have been in a museum years ago. The power distribution system alone has so many serious flaws that a major cable blowout is imminent. This would paralyse vast sections of the underground while new, horrifically expensive cable is installed and commissioned. In my opinion what should have happened years ago is the scrapping of the 4-rail system and the gradual switching of the power source from DC to AC which is vastly less expensive to supply and distribute. The fault prone shoe power collector on the trains could then be replaced with other mechanisms such as a wheel and the power track mounted on the side of the tunnel and not the floor. To take the changes even further, the trains could run on pneumatic tyres and run on a concrete track thus being almost completely silent.
- Tommo, Brighton, England, 29/07/2010 17:37
Report abuse
I love this ironic comment from Tony Travers: “The Treasury just don't trust London Underground any more.”
The Treasury's record on transport over the years is unbelievably bad.
The disastrous PPP was cooked up in the Treasury. But their greatest transport crime was the crazy industry structure forced on the railway industry at privatisation, completely against the advice of all the experts who knew anything about railways. This almost lead to the complete collapse of the network in 2000, and has resulted in a tripling in the subsidy without anything like a tripling in the quality. Our railway is now very expensive by European standards, but nothing like European quality. Have we ever has an apology from Sir Steve Robson, former deputy permanent secretary to the Treasury, who Christian Wolmar says "pushed through the structure of rail privatisation...that is at root of so many of the railway’s problems"?
There are many other examples.
More generally, the Treasury (and the ex-treasury hacks who dominate the upper reaches of the DfT) has an obsession with competition, which just doesn't work with public transport. See for example the book by Paul Mees.
London desperately devolved control over tax and spending. We need to wrest control of the purse strings from the dead hand of the Treasury, and allocate the money according to local priorities, and not according to Treasury prejudices and dubious cost/benefit models.
- Kev, Bromley, 29/07/2010 14:41
Report abuse
The problem is that the tube is run for the benefit of greedy union employees and private contractors with the paying customer only an afterthought. Its fairly simple
- George, London, 29/07/2010 14:21
Report abuse
Morning:
5°c